• NAME OF RESEARCH

    KHANI 5 HPP PRE-FEASIBILITY STUDY

  • NAME OF AUTHOR

    Deloitte Consulting

  • CATEGORY

    Energy

  • YEAR

    2013-03-27

  • Download PDF

The site of the proposed Khani 5 Hydropower Plant Project (HPP) is located in the Baghdati district of western Georgia’s Imereti Region. The potential hydropower project involves construction of an approximately 5.8 Megawatt (MW) run-of-river Hydropower Plant (HPP) on the Khanistskali River.

Pre-feasibility studies include following topics: Project area social characteristics, baseline conditions, geology ,hydropower project description, power and energy studies , project cost estimation and constrution schedule.